Monday, June 21, 2010

Elevator Report

Latest report on the elevator project:

Week of 6/27:


Underpinning of elevator shaft complete
Continued demo of former nursery areas and 1West room on first level
Commence demo of old B2 room to lay groundwork for new interior ramp

The relocation/consolidation of all classes and nurseries is now complete.

Pat Canavan

0 Comments:

Post a Comment

<< Home