Monday, May 17, 2010

Elevator Project Schedule

Here is a schedule of events concerning the elevator project. By "basement" is meant the middle building area known as the B Rooms.

Week of 5/10: partitions installed and electric service isolated in the project area
Week of 5/17: Basement ceiling and wall demolition; Mechanical, plumbing, fire protection isolated to project area; basement area is designated a hard hat area.
Week of 5/24: Continuation of ceiling and wall demolition; Basement excavation and underpinning work commences